Phase 2 slipped to 19 January at Monday's steering committee. Andrea Vogt accepted it, but on the condition it's the last slip she can defend to the board.
You have three open commitments on this project:
- The written cost delta for the 11-week slip, due 12 Sept, four days late. Priska needs it before board papers close on the 28th.
- Reconfirm the January date with the integration vendor, due 23 Sept.
- Marc Dubois owes you the Romandie test fixtures, due 19 Sept. That's the gap that caused the August regression, so it's worth chasing.
One thing worth knowing before you write the cost delta: in the technical session on 8 September, Marc's team costed mainframe write-back at eleven weeks against a twelve-week phase, and it was dropped permanently rather than deferred. If the board asks why the number moved, that decision is the answer.
Assistant
Drafting from the steering committee minutes and the kickoff scope…